Monday, March 30, 2015

Cabinets & Counter tops

The hard quartz countertops arrived Tuesday along with the extra pieces of quartz for the ensuite. Tile work was started on the ensuite, everything is coming together nicely.  The plumber installed the toilets in the main bath and the guest bath however we did not install the toilet in the ensuite as there is still too much activity there with all of the tile work in the shower and the stair risers to the jetted tub.

Tuesday, March 17, 2015

Surprise

We've had a couple of surprises in this project with electrical junction boxes behind shower walls and now a dryer vent pipe with a broken connection in the basement.  The worst surprise is during the original construction, someone cut the top cord of the engineered floor joist to install the exhaust venting for the dryer, and compromised the strength of the joist.  To correct the problem we are installing the dryer vent inside the wall, this will miss the floor joist and create a proper connection for future dryer hook-ups.  The floor joist is truly compromised, we will add framing posts between the bottom of the joist and the floor.

Monday, March 16, 2015

Preparation & Flooring

Lots of prep work to ensure the floor tiles have the right base. All of the old holes in the floor from heat registers, toilets, bidet and plumbing pipes were repaired then leveled with flooring compound.  Orange Ditra mat was used over the entire floor this provides an uncoupled flooring system and eliminates the possibility of any cracking of tiles or grout lines.  The tile work on the flooring is now complete, we expect another week for the wall tiles.  Cabinets were delivered and will be installed Monday March 16.  All of the hard surface counter tops and and extra pieces for the shower were ordered, big changes by the end of the week.

Monday, March 9, 2015

Paint & tile

All of the walls are painted with the primer coat and the first coat of paint, preparation of the walls and floors is complete and the tile work has started.  We are well behind where we should be, trades are busier than expected and dancing from one job to the next.

Monday, February 23, 2015

Drywall

The delay in the delivery of the shower has had a bit of a domino effect with both plumbing and drywall fortunately we are now past that.  The drywall crew did a great job today, all the board is up and taped, finish coat and polish coat complete by Friday.  We removed about 95% of the old Poly B pipe and replaced it with PEX pipe for all water supply lines. The tank-less Hot water system  has been started and will be complete by Friday.  The finishing Carpenter will start the trim work by Friday and the Painter will should be complete Wednesday next week in time for the new cabinets.  Tile work will start as soon as the painter has the second coat on plate.

Saturday, February 7, 2015

Demolition

Good progress over the past 3 days, all of the cabinets, and flooring were removed.  The tile was removed from the en suite tub and stairs as well as the full bath around the tub.  The wall creating the new custom tile shower in the en suite and the walls for the new full bath were also framed.
There is usually a surprise or two in any renovation, the one surprise we found so far was two hidden electrical junction boxes behind the en suite shower!  Looks like someone did a previous renovation at some time and failed to do it right.  Our electrician pulled an electrical permit and will make it right.